Kirkby Malham Bridge is a single arch masonry Grade 2 listed bridge (which spans Kirkby Beck) that required widening for safety reasons. There were no existing footpaths on the bridge but the widening allowed for footpaths to be incorporated. The bridge is at the bottom of an incline, just adjacent to the main crossroads in the centre of the village, and there had been accidents in the past due to the narrowness of the bridge and poor sight lines at the junction. The bridge parapets had also been impacted and damaged by errant vehicles.
GENERAL OVERVIEW
PROGRAMME OF WORKS
The works were carried out in phases as required by North Yorkshire County Council.
Phase 1
Installation of the scaffolding/temporary support works
Install temporary bridge across the existing bridge
Install sheet piles and excavate to extend abutments
Phase 2
Remove existing road surface
Remove existing curb line/verge line
Remove existing drain outlet
Excavate existing earth works
Phase 3
Dismantle existing bridge section, including abutments
Dismantle existing parapet
Dismantle existing side wall parapets
Phase 4
Excavate working areas
Excavate ground for foundations
Install formwork for foundations
Case concrete foundations
Phase 5
Construct new abutment stone work
Construct new bridge arch stone work
Cast concrete mass infill
Construct new bridge parapet
Construct new stone work parapet and side walls
Cast concrete mass infill sections/install dowels
Remove scaffold/temporary works
Phase 6
Install new curb line
Install new verge line
Install new drain outlet
Install new 2.No ducts
Install new road surface
Install new road markings
Phase 7
Remove traffic management
Remove temporary bridge
Phase 8
Removal of all site waste, including materials and equipment.