Cinder Track – Scarborough to Burniston

  • Client: Scarborough Borough Council
  • Location: Scarborough to Burniston
  • Value: £399,000
  • Period: May 2022 – August 2022

GENERAL OVERVIEW

Widening of existing and construction of new tarmac surfacing cycle path across the following area:

  • Wykeham Street to Manor Road Section approx. 750m length
  • Manor Road to Gallows Close Section approx. 1000m length
  • Gallows Close to Scalby Section approx. 2000m length

SCOPE DELIVERED

Wykeham Street to Manor Road Section approx. 750m length:

  • Side out 500m x 2no sides of existing footpath to allow full width use of path
  • Construct 1m widening to existing main footpath over 20m length
  • Construct 750mm widening to existing east bound link footpath over 100m length
  • Installation of 2no Kedel plastic spey benches
  • Installation of shared use path signage

Manor Road to Gallows Close Section approx. 1000m length:

  • Removal of redundant pedestrian counter at field entrance
  • Removal of existing timber gate to field entrance, installation of 2no droppable steel bollards for access purposes
  • Construct 1.5m widening to existing footpath over 460m length, including surface course overlay to existing section of footpath
  • Full construction of new 2m wide footpath over 250m length, adjacent to new wildlife and flower bund 2m wide & 300mm high
  • Planting of 25no tree whips
  • Construct 1m widening to existing footpath over 30m length
  • Reconstruction of link paths at junctions with existing footways
  • All excavated material retained on site and spread across existing field
  • Installation of shared use path signage
  • Re-orientation of existing lighting column lanterns to suit position of new footpath

Gallows Close to Scalby Section approx. 2000m length:

  • Side out existing footpath, prepare and overlay with binder & surface course to 1400m long section of main track
  • Resurfacing of various link paths up to 100m in length, including full reconstruction of Danes Dyke link path 90m long
  • Widening & overlaying existing footpath over 60m long viaduct
  • Remove existing concrete bollard and install new steel bollard to viaduct
  • Adjust existing gullies across viaduct to suit new footpath levels
  • Installation of shared use path signage
  • Improvement of path access at timber gate sections by removing unnecessary panels