Beck Hole Bridge Maintenance Works

  • Client: North Yorkshire Council
  • Location: Beck Hole Road, Beck Hole, Whitby
  • Value: £73,000
  • Period: February 2023 – March 2023 (6 weeks)

GENERAL OVERVIEW

Maintenance work to Beck Hole Bridge which is a Grade 2 listed structure.

SCOPE DELIVERED

  • Installation of scaffolding to both sides of the bridge
  • Take down of parapet walls on both sides of the bridge
  • Installation of no fines concrete to strengthen bridge and foundations for new parapet wall
  • Rebuild parapet walls
  • Installation of new road gullies and drainage
  • Resurface bridge deck
  • Take down scaffolding

SUB-CONTRACTORS

  • BDS – Surfacing
  • Keystone Conservation – Masonry works
  • Sky Scaffolding – Scaffolding
  • Oneway TM – Traffic Management
  • Clearway – Gully cleaning