Burniston Bridge Strengthening & Drainage Works

  • Client: North Yorkshire Council
  • Location: Iansfield Industrial Park, Burniston Road, Scarborough
  • Value: £100,000
  • Period: February 2023 – April 2023

GENERAL OVERVIEW

Strengthening of the bridge to increase load capacity and installation of new drainage to help reduce flooding on the carriageway.

SCOPE DELIVERED

  • Road surface dug out to expose the barrel of the bridge followed by backfilling with 26m3 of concrete, finishing with binder and the laying of surface course tarmacadam
  • Some areas of the parapet walls taken down and and rebuilt
  • Existing parapets then repaired and reinstalled
  • Installation of a series of manholes connected with 225mm perforated pipes