Broughton Flood Mitigation Works

  • Client: North Lincolnshire Council
  • Location: Brigg Road, Broughton, North Lincolnshire
  • Value: £150,000
  • Period: January 2023 – March 2023 (9 weeks)

GENERAL OVERVIEW

Installation of new drainage alongside associated kerbing works and carriageway surafcing.

SCOPE DELIVERED

  • Excavation of existing verge areas on both sides of the carriageway
  • Installation of 450mm perforated twin walls pipes connected by a series of newly installed manholes
  • Manholes fitted with gully covers to allow surface water run off from the carriageway
  • Installation of new kerb line to carriageway junction
  • Existing surface course of carriageway planed off with new surface course layer laid after completion of drainage

SUB-CONTRACTORS

  • Oneway TM – Traffic Management
  • BDS – Carriageway surfacing
  • Trustseal – Road studs & Line marking