Holderness Road (Diadem Grove to Ganstead) Carriageway Reconstruction & Resurfacing

  • Client: Hull City Council
  • Location: Holderness Road, Hull
  • Value: £603,000
  • Period: January 2021 – May 2021

GENERAL OVERVIEW

This project consisted of carriageway reconstruction and resurfacing to Holderness Road (between Diadem Grove and Ganstead). The works were carried out in two phases, with full traffic management, as detailed below:

Phase 1 (Outbound Holderness Road)

  • Planning
  • Ironworks
  • Excavation
  • Concrete repairs
  • Joint/crack treatment
  • Surfacing
  • Application of anti-skid and line markings

All of the works were carried out under a full road closure of the outbound carriageway. Access to the BP petrol station on the outbound side was maintained at all times via the inbound carriageway.

Phase 2 (Inbound Holderness Road)

  • Planning
  • Ironworks
  • Excavation
  • Concrete repairs
  • Joint/crack treatment
  • Surfacing
  • Application of anti-skid and line markings

All of the works were carried out under a full road closure of the inbound carriageway. Access for residents was maintained at all times via the outbound carriageway.